Board adopts Resolution No. 41-26 to authorize final payment of $565,874.13 for county chloride program

Aug 4, 2026

Commissioners adopted Resolution No. 41-26 accepting the completed CM 2026-03 Roadway Chloride project and authorizing final payment of $565,874.13 to Edwards Oil, Inc. dba Trimark Industrial.

The full story

County Engineer Darrick Anderson presented Resolution No. 41-26 for the Board’s consideration, reporting that the final contract cost for the CM 2026-03 Roadway Chloride project was $565,874.13. Anderson said that converting some roadways treated with chloride to paving could yield long-term cost savings, and he asked the Board to adopt the resolution to accept the completed project and authorize final payment to the contractor, Edwards Oil, Inc. dba Trimark Industrial.