CDD authorizes RG Architects subconsultant work for $62,500 gatehouse redesign

Oct 22, 2024

The board authorized Bowman to retain RG Architects as a subconsultant to redesign two gatehouses, approving a reimbursable up-front design cost of $62,500 and anticipating design/permitting will take 12–18 months with construction beginning after financing in 2026.

The full story

The River Ridge CDD voted to authorize Bowman to retain RG Architects, P.A. as a subconsultant to redesign two gatehouses at the River Club complex and related sites. The board discussed that the gatehouses will not be demolished but will undergo a 'facelift' and that design and permitting are expected to take 12–18 months. The transcript records that the project cost for initial design was discussed to be booked as a reimbursable expense and invoiced when financing is issued.