Board hears bond-construction progress: cafeteria groundwork, middle-school exterior work
Dec 16, 2024
Dec 16, 2024
WRA architects and Mazanec Construction told trustees they are reviewing punch-list items, furniture deliveries are arriving, groundwork and foundation work for a new cafeteria has started, the middle school will be re-skinned externally, and tile replacement in a hall is complete.
The full story
Representatives from WRA architects and Mazanec Construction updated the Board of Trustees on bond-funded construction progress. They reported that punch-list items are being reviewed and that furniture deliveries are in progress. "Ground work and foundation has been started for the Cafeteria addition," the minutes state.