District construction remains on schedule; ductwork and electrical work underway
Summary
Project contractors reported that ductwork has started, electrical outlet locations are approved, A/C units will be set next and Conduent will be installed; the project remains on schedule and trustees were invited to tour the new building.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Contractor representatives from SZS and project staff told trustees that the construction project is progressing on schedule.
"The duct work has been started and all electrical outlet locations have been approved. Next the A/C units will be set and Conduent will be installed. The project is still on schedule," the minutes record from Abigail LaRussa (SZS) and Zach Mikulenka. Superintendent/administration invited trustees to tour the new building; no change orders or schedule delays were reported during the update.
The report was informational; the board did not take action but accepted the update and will monitor progress through staff reports and site visits.