Board updated on progress of Pewitt CISD new elementary school
Summary
Godwin Architects and Jackson Construction gave trustees an update on the district's new elementary school project, outlining construction progress and next milestones; the board later approved a construction payment application.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
Architects Jordan and Derrik Godwin of Godwin Architects and Jaxon Hevron of Jackson Construction briefed the board on the status of the new elementary school project. They summarized recent on-site progress and the next steps needed to keep the schedule on track.
Following the update, trustees approved Certification of Payment Application #8 to continue project funding flows; Mark McCoy moved and Justin Green seconded the approval. The board also reviewed related budget items during the meeting's financial reports.