Contractor reports earthwork, utility and foundation progress at junior high site

Buffalo ISD Board of Trustees · April 27, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Contractor 'Chris' told trustees the upper junior high West Side is roughly 2.5 feet from target elevation, settlement monitoring is underway, utilities and foundations will start soon, and lighting fixtures submitted meet the fixture schedule.

A contractor identified in the meeting as 'Chris' presented a construction progress update for the new junior high and answered trustees’ questions about grading, utilities and site features.

"We're continuing to hauling dirt on the upper junior high on the West Side," Chris said, adding the West Side infill is about 2.5 feet from target elevation and the team will watch for settlement with Tier Con and GLS. He told trustees that foundations and structural work on the East Side should begin in the coming weeks while settlement monitoring continues on the West Side.

Chris described water‑line work around the football field and running lines to a final fire hydrant; he also said the contractor's submitted lighting fixtures are from approved manufacturers and meet the fixture schedule. Trustees asked about detention, retaining walls and generator sizing; the contractor confirmed a retaining wall is planned on one side of the site and that a building that size likely would require multiple generators.

Superintendent (speaker 4) and board members agreed to continue monthly construction updates and invited trustees to perform on‑site walkthroughs. No formal action was taken at the end of the presentation.