Bastrop ISD reports progress on bond projects including Adelton Elementary and Mina rebuild

Board of Trustees, Bastrop Independent School District · January 28, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Construction and design updates: Adelton Elementary is reported 25% complete, Mina Elementary rebuild is 2% complete, middle school weight rooms are nearly finished, and high school classroom wing is in design phase.

Lee Raspberry, Director of Construction & Planning, updated the board on the district’s 2021/2023 bond program status and key facilities projects.

Raspberry reported near-complete weight rooms at Bastrop and Cedar Creek Middle Schools (99% complete), Adelton Elementary at 25% complete, Mina Elementary rebuild at 2% complete, and the Bastrop High School classroom wing in the design phase. He said the new Police and Operations Facility construction had begun this month and other additions and renovations were on schedule.

Board members received the facilities & operations report and asked clarifying questions. Staff will continue to provide regular bond updates as projects proceed.