Bond construction update: district hears options for computer classroom electrical work; cafeteria piers nearing completion
Summary
WRA and Mazance Construction briefed trustees on options to provide additional electrical capacity for Ms. Gillaspy’s computer classroom and reported progress on cafeteria piers and other site work; BEEF pledged $15,000 for graduate scholarships, the superintendent reported.
Get email alerts on the Bond Construction topic
No spam. Unsubscribe anytime.
District construction consultants WRA and Mazance Construction presented design options at the Feb. 19 meeting to meet higher electrical demands for Ms. Gillaspy’s computer classroom, discussing tradeoffs between adding floor boxes and installing ceiling dropdowns to supply power for advanced instructional technology.
Superintendent Mr. Skeeler updated the board that construction piers for the new cafeteria are being completed and that the entryway and windscreen are nearing completion. The superintendent also reported that BEEF pledged $15,000.00 for graduate scholarships, a funding note the board recorded during administrative reports.
Trustees did not take an action on construction options at the meeting; the presentation provided staff direction and technical comparison points for later contract or change‑order decisions. The board’s next steps will be driven by staff recommendations and any required change orders to current construction contracts.