County approves $5.75M GMP amendment for Teton Pass Trail construction

Teton County Board of Commissioners · July 7, 2026

Summary

The Board approved Whitaker Construction’s CMAR GMP Contract Amendment #2 for Teton Pass Trail segments 1–3 totaling $5,745,569; $3,749,971 is reimbursable by the BUILD grant, local share $937,493, and $1,058,105 philanthropic funding.

The Board approved a Construction Manager at Risk (CMAR) Guaranteed Maximum Price Contract Amendment #2 for construction of BUILD Grant Project Component 7 — the Teton Pass Trail (segments 1–3).

Brian Schilling, Pathways & Trails Program Coordinator, presented the amendment, answered commissioner questions and received public comment from Tim Young. The Board voted to approve Whitaker Construction’s CMAR Contract Amendment #2 in the amount of $5,745,569.00. The staff materials recorded that $3,749,971.00 of that total is reimbursable by the BUILD grant; a local FY2027 Fund 37 share of $937,493.00 is included in the approved FY2027 budget; and $1,058,105.00 is philanthropic funding pledged to support the project. The Board encouraged staff to advance single‑lane traffic construction as feasible to Coal Creek.

The amendment funds construction for trail segments 1–3; the BUILD grant reimbursement and local budget allocation are recorded in the staff recommendation.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source