Text amendment clears local planning panel; rezoning and referendum remain possible for any data-center project

Clark County Rural Zoning Commission · June 11, 2026

Summary

The Planning Commission recommended approval of the draft with USDA prime-farmland language; the RZC recommended approval and noted that any data-center project would require rezoning to I-2 (subject to public hearings and possible referendum) and standard notices are sent to property owners within 200 feet.

The Clark County Planning Commission reviewed the draft on June 3 and recommended approval with the addition of the USDA prime-farmland language; the Rural Zoning Commission echoed that recommendation on June 11. Mrs. Dunlap explained that the text amendment itself would be adopted by the County Commissioners and that any proposed data-center site would require rezoning to I-2 before a conditional-use application — and that a rezoning approved by the commissioners could be subject to a referendum and public vote.

Commissioners discussed notification practices and whether data centers warranted wider notice. Mrs. Dunlap said notices are currently sent to anyone within 200 feet and that the case would appear on the website and in the newspaper; some commissioners suggested broader notice for property-value analysis and impact studies, but staff did not propose changing the standard notice radius in the text amendment.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source