Blight Elimination Program funds spur accelerated demolition timeline; contractor pledges Sept. 1 completion

Manistee County Land Bank Authority · July 7, 2026

Summary

Consultant Susan Wenzlick told the Land Bank the project was put on an accelerated schedule because Blight Elimination Program funds were reallocated; a Pitsch Companies representative confirmed the firm can complete the asbestos abatement and demolition by Sept. 1, 2026 to secure grant reimbursement.

The Manistee County Land Bank Authority heard that the demolition and asbestos-abatement project for 267 Third Street was placed on an accelerated schedule after Blight Elimination Program funds were reallocated following the cancellation of another project in Bear Lake. Consultant Susan Wenzlick said the availability of those funds necessitated a compressed timeline to preserve eligibility for state reimbursement.

A representative of Pitsch Companies confirmed the firm could meet the schedule and complete the work by Sept. 1, 2026. Authority members and staff discussed the importance of timely documentation and noted the project timeline was updated after the contract approval to align with grant reporting requirements.

Staff will proceed to finalize contracts and to track required deliverables so the Authority can file for reimbursement within the State Land Bank Authority deadlines.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source