Development update: transmission main advancing; impact-fees hearing scheduled

Apr 15, 2026

City staff reported that transmission-main trenching and related installation work are substantially complete and announced a public hearing and ordinance on impact fees scheduled for April 28; the Highway 29 relocation was described in the transcript as '9999% complete' (as spoken).

The full story

City staff summarized development and utility-engineering work in the city, reporting that the transmission main and trenching were at about 95% completion and installation approximately 65% complete, with testing of installed sections to begin soon. An elevated storage tank has been issued a notice to proceed, and wastewater treatment plant submittals have been reviewed; coordination with PEC on transformer contracting was noted.