District lists completed facilities upgrades, with some projects delayed and contractor damages withheld

Aug 11, 2026

Staff reported 25 of 39 planned 2025–26 facilities projects completed (totaling $2,769,485), highlighted work at Gilchrist and Ferguson, and said the district withheld $42,000 (total $54,853.96 recouped) in liquidated damages from contractor DCI after missed deadlines on the children's gym contract.

The full story

Facilities staff gave a multi-part update on capital projects completed in 2025–26 and those still in motion. The district reported an approved list of 39 projects budgeted at $2,994,300 and said 25 projects were finished by June 30 at a cost of $2,769,485; staff provided line-item examples including window and roofing work, gym and cafeteria upgrades at Gilchrist, and the completed children's gym.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in