Library rooftop solar installation underway; Solect expects Certificate of Completion mid-July

Jul 13, 2026

MSOC was told the library rooftop solar installation began June 11; Solect expects a Certificate of Completion by July 15 followed by Schedule Z filing, witness test and an Eversource permission-to-operate before the end of 2026.

The full story

Committee members received a status update on the Sharon Public Library rooftop solar project. Allen Giles of Solect told the committee that installation began June 11 and that Solect expected to provide a Certificate of Completion by July 15. Following certification, the project team planned to submit a Schedule Z application, conduct a witness test and seek permission to operate (PTO) from Eversource, with the PTO anticipated before the end of calendar year 2026.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in