MSOC was told the library rooftop solar installation began June 11; Solect expects a Certificate of Completion by July 15 followed by Schedule Z filing, witness test and an Eversource permission-to-operate before the end of 2026.
The full story
Committee members received a status update on the Sharon Public Library rooftop solar project. Allen Giles of Solect told the committee that installation began June 11 and that Solect expected to provide a Certificate of Completion by July 15. Following certification, the project team planned to submit a Schedule Z application, conduct a witness test and seek permission to operate (PTO) from Eversource, with the PTO anticipated before the end of calendar year 2026.