MSOC was told the library rooftop solar installation began June 11; Solect expects a Certificate of Completion by July 15 followed by Schedule Z filing, witness test and an Eversource permission-to-operate before the end of 2026.
Get email alerts on the Library Solar topic
No spam. Unsubscribe anytime.
Committee members received a status update on the Sharon Public Library rooftop solar project. Allen Giles of Solect told the committee that installation began June 11 and that Solect expected to provide a Certificate of Completion by July 15. Following certification, the project team planned to submit a Schedule Z application, conduct a witness test and seek permission to operate (PTO) from Eversource, with the PTO anticipated before the end of calendar year 2026.
Members noted the remaining steps for interconnection and that the Schedule Z and witness test are prerequisites to Eversource issuing PTO. The transcript records projected milestone dates (Certificate of Completion by July 15; PTO anticipated before the end of 2026) but does not include a firm, signed PTO date from Eversource.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.