Board approves $4,600 change order for annex tuckpointing as courthouse renovation proceeds

Jul 28, 2026

River City submitted Change Order No. 15 for $4,600 to complete additional tuckpointing on the historic annex; approval leaves a contingency balance of $7,788.50. County Administrator John Gorton reported the third-floor courtroom demolition and remediation are complete and HVAC work is scheduled to start Aug. 10.

The full story

The Board approved Change Order No. 15 in the amount of $4,600 for additional tuckpointing work on the historic annex of the Meriwether County Courthouse. County Administrator John Gorton said the work would be paid from the project contingency and that approval would leave $7,788.50 in contingency funds.