County project near substantial completion; DOC inspection set for mid-September

Hubbard County Board Work Session · August 12, 2026

Summary

A county construction presenter said the government center, garage and much of the jail are complete; Units B and C are occupied and Unit A is finishing with a Department of Corrections inspection scheduled Sept. 14 and turnover anticipated later in September.

A construction presenter updated the board on the LAC project and said multiple components are complete and turned over to the county. "We do have DOC inspection scheduled for September 14," the presenter said, and described the inspection as a verification that security systems are operating before final occupancy.

The presenter said Units B and C in the jail have been completed and are occupied and that Unit A remains in the last phase of work with glazing and painting to finish. He said the project team has been meeting biweekly for oversight and that site work, security railing installation, epoxy finishes in showers and other punch items are being completed ahead of final closeout and turnover.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source