Trinity ISD gets update on Lansberry Elementary addition; utilities connected
Summary
District staff reported that utilities for the Lansberry Elementary addition are connected, inspectors noted unfinished items, and overall work is progressing as expected, the board heard June 22.
Get email alerts on the School Construction topic
No spam. Unsubscribe anytime.
Gill Campbell provided the board a construction progress report on the addition to Lansberry Elementary, saying that "utilities are connected." The update noted that an inspector observed some unfinished jobs but that overall progress is "moving along as expected."
The report was presented during the regular board meeting at the Trinity ISD administration building. Board members did not take formal action on the construction update; the item was presented as informational. The update included a short list of remaining tasks identified by the inspector; no schedule changes or new costs were announced.