Board discusses construction close‑out, warranties and ongoing maintenance needs

Nov 10, 2025

Trustees reviewed final construction payments, warranty expirations on the new building and maintenance needs such as restroom repairs and gym floor work; superintendent noted the district paid the construction manager and is addressing lingering repair/warranty items.

The full story

Board members reviewed construction close‑out items after the recent bond projects. Trustees were told the construction manager at risk received final payment and the district now owns and is maintaining completed facilities. The superintendent noted warranty expirations and cited an example: "We spent $14,300,000 and you get a 1 year warranty," and discussed follow‑up with the contractor on items such as locked doors, restroom stalls and paint that is peeling in the crow's nest.