Contractor reports progress on McCamey ISD Phase 2 construction

McCamey ISD Board of Trustees · April 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A Gallagher Construction representative updated the board on Phase 2 work including gym paver and metal panel installations, asphalt paving, and high-school terrazzo floors and window installations.

Gilbert Bustos of Gallagher Construction appeared at the April 23 meeting to brief trustees on Phase 2 of the district construction program.

According to the minutes, gymnasium work includes paver installations, metal panel installations and Gallagher asphalt paving. High school work in progress includes terrazzo floor installations, glass window installations, soffit and parapet work, steel erection and brickwork. The update was received; no formal board action on construction was recorded in the minutes.