Public works Director Denham said SR20 corrective action work is scheduled for Sept. 16 and that wastewater treatment plant startup procedures are under review; "Testing and training will begin on Thursday and will take up most of his and the public works crew’s time," he reported.

Director Denham reported the corrective action work plan for SR20 is scheduled for Sept. 16 and said wrap-up and project closeout should be completed soon. He thanked his crew for addressing a problem proactively before management became aware of it.

On the wastewater treatment plant, Denham said the review of startup procedures has begun and that "testing and training will begin on Thursday and will take up most of his and the public works crew’s time." Staff will balance winterization tasks with the training schedule while getting the plant ready for operations.