Sewer lateral lining underway; hydrant replacement planned, borough says
Feb 4, 2025
Bally officials reported that Performance Pipeline's lateral lining and televising work is progressing and that crews will replace a broken hydrant used by bulk-water customers, with the old hydrant rebuilt for reuse elsewhere in the borough.
The full story
Public works staff told council that the current sewer lateral-lining project by Performance Pipeline has progressed smoothly: crews televised lines last week, are installing 'vac-a-tees,' and expect to begin actual lining in about two weeks.