Committee sets 180/365 timeline for data center decommissioning
Aug 10, 2026
The subcommittee added a start and completion cadence to the draft: decommissioning must begin no later than 180 days after abandonment and be completed within 365 days, with members clarifying the countdown should start at the date of decommissioning.
The full story
The draft's timeline provisions were clarified during discussion: the ordinance will require that decommissioning, recycling and site restoration be completed within 365 days after abandonment, discontinuation, or a declaration of public nuisance, and a member proposed inserting a requirement that work begin no later than 180 days after the decommissioning date.