Subcommittee backs 150% performance bond, county‑approved engineering estimate for data centers

Aug 10, 2026

Grant County subcommittee agreed the ordinance will require a bond equal to 150% of estimated decommissioning costs based on an engineering study by a certified firm acceptable to the county; members debated review frequency and whether the bond may be adjusted downward.

The full story

The subcommittee revised the draft to require a performance guarantee in the form of a bond only, in an amount equal to 150% of the estimated cost of decommissioning, recycling and site restoration. Members agreed the estimate must be produced by an engineering study conducted by a certified engineering firm acceptable to Grant County and that the bond should be adjusted to reflect updated estimates.