Board hears Bond 2024 update; GMPs for major campus projects due April 29

Highland Park Independent School District Board of Trustees · April 22, 2025

Summary

Assistant Superintendent Scott Drillette presented Bond 2024 project timelines and said Guaranteed Maximum Price documents for Armstrong, MIS/HPMS and HPHS are expected April 29, with construction slated to start this summer.

Assistant Superintendent for Business Services Scott Drillette told trustees the Board received an update on Bond 2024 that included timelines and project details from VLK Architects and Lee Lewis Construction. He said "Guaranteed Maximum Price (GMP) documents for Armstrong, MIS/HPMS, and HPHS are expected to be submitted to the Board on April 29."

The minutes record that the GMP documents will be scheduled for review and approval in May and that construction is set to begin this summer. No GMP dollar amounts or changes to scope were recorded in the public minutes.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source