County engineer reports contractor error on 235th Road bridge; Route W46 paving preconstruction set for Aug. 4

Van Buren County Board of Supervisors · July 27, 2026

Summary

County Engineer Ryne Thornburg said the contractor on the 235th Road bridge replacement made an error that required a minor plan revision (at contractor expense) and that the Route W46 paving preconstruction meeting is scheduled for Aug. 4, 2026.

County Engineer Ryne Thornburg told the Van Buren County Board of Supervisors July 27 that the contractor working on the 235th Road bridge replacement has made an error requiring a minor revision to the plans and that any additional costs arising from that error will be the contractor’s responsibility. Thornburg said work is making progress despite the revision.

Thornburg also announced that a preconstruction meeting for the Route W46 paving project, covering the stretch from the Farmington city limits to Route J40 (east of Harmony Elementary School), is scheduled for Aug. 4, 2026. The Board took the update as informational; no new funding or contract actions were recorded in the July 27 minutes.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source