SDDOT reports June net contract decrease; I‑229 work added and several high-value CCOs noted
Aug 13, 2026
SDDOT reported a June net decrease in Construction Change Orders (CCOs) of $2,426,974.28 and a 12‑month net change of 1.51%; a notable I‑229 contract had a $463,611.78 (26.2%) CCO for added concrete repairs and overlay work at Exit 6.
The full story
Ryan Johnson of the Office of Operations Support presented departmental CCOs completed in June and highlighted projects where changes exceeded $100,000 or 25% of original contract amounts. June CCOs showed a net decrease of $2,426,974.28; over the past 12 months the total change to original contract amounts has increased by 1.51%.