Leet Township approves Youngblood Paving final payment and records net contract decrease
Summary
The Board approved final Pay Request #1 of $48,417.88 to Youngblood Paving for the 2024 Liquid Fuels Roadway Improvement Program and approved Change Order #2 reducing the contract by $20,537.42 after projected base repairs were not needed.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Engineer John Valinsky reported Youngblood Paving completed the Watson Street work and installed a speed table on Plum Street; he noted a minor ponding issue that will be corrected and that the projected base repair on Watson Street was unnecessary. The Board approved Pay Request #1 Final for $48,417.88 and approved Change Order #2 for a net decrease of $20,537.42 reflecting the reduced scope.
Valinsky indicated a pothole at a resident’s house was not part of the project but that township crews or Foreman Wanto might repair it with cold patch. The motions passed by roll call with unanimous yes votes recorded in the minutes.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.