Developers press for clearer self‑build rules as tariffs and supply chains bite
Summary
Developers and EDF told the committee that allowing developers to procure or construct interconnection/network upgrades and equipment could ease supply‑chain bottlenecks, but IOUs cautioned that specifications, system differences and liability concerns make standardization complex.
Industry witnesses urged clearer policies on developer 'self build' of interconnection facilities and network upgrades to offset tariff‑driven supply bottlenecks. Sarah Fitzsimon and Rachel McMahon said many developers have relationships with equipment suppliers and could help procure transformers, breakers or even construct some upgrades; McMahon noted developers often buy the same equipment as utilities and could alleviate delays if permitted.
Gary Chen of Southern California Edison said SCE is open to self‑build where projects can meet utility safety and reliability specifications but cautioned a one‑size‑fits‑all standard is unrealistic because systems are built differently across utilities and affected systems require coordination. Panelists recommended deeper, project‑level conversations and potential standardization for specific equipment classes where feasible.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.