San Diego pilot would require faster utility energization timelines for public benefit projects

Apr 22, 2026

AB 25 18 establishes a five‑year San Diego pilot with category‑specific utility energization timelines (40 business days for affordable housing, 55 for municipal/EV, 70 for others) to reduce delays that are delaying occupied affordable housing projects.

The full story

Assemblymember Sharp‑Collins told the committee that AB 25 18 is a targeted pilot to address lengthy and unpredictable utility energization delays that impede affordable housing and other public benefit projects. Frances Baraza of the San Diego Housing Commission described a Homekey supportive housing project that had multi‑week energization delays and said a 40‑business‑day timeline for category‑one projects would have prevented the harm.