Council approves final payment and $71,000 decrease for Highway 12 water-main project
Nov 12, 2025
Nov 12, 2025
The city engineer recommended and council approved the final payment application and change order that reconciles contract quantities and reduces the Highway 12 water-main contract by $71,000; the motion passed 4-0.
The full story
The City of Montrose council approved the final payment application and change order for the Highway 12 water-main replacement project, a staff report said. The city engineer told council that change order number 1 reconciles final contract quantities and results in a decrease to the contract of $71,000; staff recommended approval and council agreed by a 4-0 vote.