County awards 2026 dust‑control contract; engineer and motion cite slightly different totals

Sheridan County Staff Meeting · April 2, 2026

Summary

Sheridan County's engineer reported one bid for the annual dust‑control project and a contract price near $446,800 for roughly 65 miles; the motion to award cited $446,880 while the engineer reported $446,808, a discrepancy flagged for contract paperwork.

County Engineer Ken Mallard said the county publicly advertised the annual dust‑control contract and received a single bid. He told the board the contractor's price rose roughly 5% from last year and stated a total contract price of $446,808 for coverage of about 65 miles of county road.

Commissioner Cummings moved to award the 2026 dust‑mitigation project to Oxford Incorporated and asked the chair to sign contract documents; the motion language cited $446,880 as the contract amount. "Their price did increase from last year's about 5%... So the total contract price would be $446,808," Ken Mallard said on the record. The board approved the motion; staff said contract documents will be cleaned up before signing to reconcile the numeric discrepancy.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source