Aquilla ISD board hears bond project update; AV overage resolution presented
Dec 15, 2025
Superintendent and a visiting contractor reported that the campus roof is about 95% complete and electricians have begun work; the board reviewed a resolution to cover additional audio-visual expenses identified in October.
The full story
Superintendent David Edison presented the board with a resolution addressing additional expenses tied to an audio-visual problem discovered in October and provided an update on the district's bond construction work. Visitor Wade Zimmer reported that "the roof is 95% complete and most of the exterior is complete," that one course of brick has been laid, metal ductwork has been staged and that electricians have begun work in earnest.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
