Aquilla ISD board hears bond project update; AV overage resolution presented

Dec 15, 2025

Superintendent and a visiting contractor reported that the campus roof is about 95% complete and electricians have begun work; the board reviewed a resolution to cover additional audio-visual expenses identified in October.

The full story

Superintendent David Edison presented the board with a resolution addressing additional expenses tied to an audio-visual problem discovered in October and provided an update on the district's bond construction work. Visitor Wade Zimmer reported that "the roof is 95% complete and most of the exterior is complete," that one course of brick has been laid, metal ductwork has been staged and that electricians have begun work in earnest.