County approves ASCO switch replacement plan for courthouse generator

Buchanan County Board of Supervisors · August 3, 2026

Summary

Buchanan County supervisors approved replacing obsolete basement transfer switches on the courthouse generator with ASCO switches, citing unavailable parts for the existing gear, a 3–5 week lead time and brief planned outages; the board authorized the chair to sign the vendor proposal.

Buchanan County supervisors voted to approve a plan to replace two obsolete transfer switches that serve the courthouse emergency power system, approving the vendor's recommended option and authorizing the chair to sign the proposal.

The presenter warned that the two basement switches are obsolete and that manufacturer parts are unavailable: "Parts are unavailable," the presenter said, noting a potential catastrophic failure if replacements are not planned. The vendor recommended ASCO transfer switches as a more reliable alternative with shorter lead times than the older ABB equipment.

The vendor described the installation process and outage planning: once ordered, ASCO switches would take roughly three to five weeks to arrive; installers would stage temp power and perform a brief outage the morning of the swap. Doing both switches in one day was estimated at about 16 hours; splitting the work into two days would be about 12 hours each. A board member noted the labeling in the switch cabinets is outdated, which complicates isolating loads during work.

On funding, a board member said capital-project funds are available: "You guys budgeted 156,207, but 45,000 of that is what you guys plan to move to the jail's capital project fund," and confirmed the capital account could cover the work. After discussion, S5 moved to approve the recommended option (option 3); the motion received a second and passed by voice vote.

The board also approved a motion authorizing the chair to sign the option‑3 proposal electronically when it is delivered as a PDF.

The decision directs staff to place the order and coordinate scheduling with the sheriff's office and other departments to minimize disruption during the required outages.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source