River Ridge awards $1.11 million contract for multi-phase drainage improvements
Apr 28, 2026
The Board approved Clark Construction’s not-to-exceed bid of $1,111,860 (including an added 5% contingency) to complete four phases of stormwater/drainage improvements covering Oak Run, Turnberry, Palmetto Dunes and Seaside IV.
The full story
District Engineer Charlie Krebs and District staff reviewed competing bids and recommended award of the River Ridge Phase 2 Drainage Improvement work covering four project areas. Krebs described unit-cost items and identified locations and likely quantities where contingency funds would be applied.