Administration building on schedule; brick supply issue resolved, pavilion bid accepted
May 12, 2026
Administration Building work is on schedule with a walkthrough set for June 8, 2026; Abigail LaRussa reported a brick-supply problem resolved by selecting a new sample and reserving material, and said the pavilion bid has been accepted.
The full story
Construction on the Flatonia ISD Administration Building is progressing on schedule, Administration staff member Abigail LaRussa told trustees at the May 12 meeting. She reported that two previously selected brick options were unavailable; the board reviewed a new sample at the meeting and LaRussa said she has reserved enough of the chosen brick for the entire project and will place the order after the meeting. A final walkthrough is scheduled for June 8, 2026.