ATV trail resurfacing bids come in 54% over estimate; board approves reduced-scope contract
Jun 23, 2026
Bids for the Sea Lion/ATV trail resurfacing exceeded available funding (engineer's estimate $200,000; low bid $308,032). The county engineer proposed reducing aggregate from ~15,000 to ~9,600 tons and the board approved awarding the contract with scope adjustments.
The full story
County engineer Mr. Hammond told commissioners that bids for project SP0026-25-3A came in significantly above the engineer's estimate. "Our low bidder came in at $308,032," he said, noting that was roughly 54% over the $200,000 funding level from a $150,000 grant plus $50,000 match. He explained market factors — higher diesel fuel prices and federal requirements — contributed to higher bids and proposed reducing the aggregate quantity and using change orders to match available funding.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
