ATV trail resurfacing bids come in 54% over estimate; board approves reduced-scope contract

Jun 23, 2026

Bids for the Sea Lion/ATV trail resurfacing exceeded available funding (engineer's estimate $200,000; low bid $308,032). The county engineer proposed reducing aggregate from ~15,000 to ~9,600 tons and the board approved awarding the contract with scope adjustments.

The full story

County engineer Mr. Hammond told commissioners that bids for project SP0026-25-3A came in significantly above the engineer's estimate. "Our low bidder came in at $308,032," he said, noting that was roughly 54% over the $200,000 funding level from a $150,000 grant plus $50,000 match. He explained market factors — higher diesel fuel prices and federal requirements — contributed to higher bids and proposed reducing the aggregate quantity and using change orders to match available funding.