Superintendent reports bond-project progress and summer projects

Williamston Board of Education · June 15, 2026

Summary

Superintendent Dr. Adam Spina reported work underway on WHS parking lots and sidewalks, flooring at middle and high schools, gas-line/internet moves at the elementary, Explorer gym footings, and a Pool Pak HVAC lift completed June 8; non-bond summer projects for 2026 and 2027 were also presented.

Dr. Adam Spina updated the board on active bond-funded projects and planned summer work. He reported that the Williamston High School parking lots and sidewalks are underway, flooring work at the middle and high schools began June 15, work to relocate a gas line and internet cabling at the elementary school is in progress, footings and foundations for the Explorer gym will begin soon, and a crane lift on June 8 placed a new Pool Pak HVAC system after removing the old unit.

Spina also reviewed a memo listing non-bond-funded district projects for summers 2026 and 2027 and noted that the list is not all-inclusive; board members asked clarifying questions and were told Brandon Weingartz will make a presentation at an upcoming meeting. The updates were presented as part of the Superintendent’s Report and recorded in the minutes.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source