Lindsay ISD: concrete poured, power and intercoms installed at new elementary

Lindsay Independent School District Board of Trustees · March 23, 2026

Summary

Superintendent Steve Cope reported that concrete has been poured for the new elementary building at 605 Elizabeth Street, permanent electricity is now connected and intercoms are being installed; cameras and doors await ceiling installation.

Superintendent Steve Cope told the Lindsay ISD Board that construction on the new elementary campus is progressing and that the building’s address will be 605 Elizabeth Street. "Concrete has been poured for the new elementary building," he reported, and permanent electricity has been connected, allowing technology and safety systems to proceed.

Cope said intercoms are being installed and that camera and door installation is pending completion of ceiling work. The update was delivered as part of the superintendent’s regular report; no action was required beyond continuing oversight and coordination with contractors and district departments.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source