AG|CM updates board on 2025 Bond Program; construction timelines extend through spring 2028

Wimberley Independent School District Board of Trustees · March 23, 2026

Summary

AG|CM representatives reported progress on the 2025 Bond Program, including site improvements, roofing and HVAC projects, ongoing contract negotiations and the start of a WHS band marching pad, with construction timelines projected through Spring 2028.

AG|CM representatives provided a bond program update during the March 23 meeting, reporting work across multiple bid packages including site improvements, roofing and HVAC projects, and the start of a WHS band marching pad. Presenters said contract negotiations and final design work continue and projected construction timelines extending through Spring 2028.

The presentation framed the bond program as multi-year work with staggered bid packages and ongoing coordination with district staff; the board was advised of upcoming considerations and next steps for implementation and contracting.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source