Engineer recommends change orders and payment for 2026 liquid fuels road program
Aug 13, 2026
Aug 13, 2026
Township engineer presented change order #2 and #3 to adjust pavement‑marking quantities and extend the contract 45 days, and recommended payment certificate #2 to Harris Black Topping for $406,024.43; the board approved the motions.
The full story
The township engineer presented items for the 2026 liquid fuels road program including change order #2 (adjust pavement‑marking quantities per PennDOT representative) and change order #3 (adjust field quantities and approve a 45‑day contract extension). The engineer recommended approval of both change orders.