Council reviews expanded Lower South Street sewer plan and engineering amendment
Apr 27, 2026
Dave Rambo and Hudson Engineering presented an amended Lower South Street sewer plan that would add a new pump station and roughly 1,700 feet of force main; project cost estimates rose from about $4.1 million to roughly $11.4 million and the council approved an amendment to the Hudson Engineering contract to move the project toward permitting and grant readiness.
The full story
Dave Rambo outlined an amended design for the Lower South Street/South Sewer Project and said the change is intended to free up properties on Water Street for future development by rerouting the sewer main and adding a pump station. He said the project requires under-railroad crossings and possible riverfront routing, and called it "a very intense project" with a roughly 1,700-foot sewer force main.