Engineering staff report progress on AMD, ROW acquisitions and Chub Run bids
Summary
Engineering staff updated the council on multiple infrastructure items: Phase 1 AMD change orders and amendments, Phase 2 ROWs (30 of 34 obtained) with DOH permit under review, Chub Run change orders and a vendor bid opening rescheduled to March 10, 2026, and Phase IV awaiting contractor remobilization.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
Engineering staff provided a consolidated update on several active projects. For Phase 1 AMD the meeting record lists Change Order 4, an Engineering Amendment 2 and a Notice of Acceptability. For Phase 2 AMD staff reported 30 of 34 right-of-way acquisitions in hand, with outstanding ROWs from two businesses, one utility and one resident; the Department of Highways (DOH) permit was under review and a to-bid meeting with AML was scheduled.
On Chub Run, staff noted progress-meeting minutes, presentation of two change orders and that the vendor bid opening was moved from Feb. 24, 2026 to March 10, 2026. Phase IV remains on hold pending contractor remobilization.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.