Engineer reports ROW progress on Phase II reclamation and delays on Chub Run sewer work
Summary
The engineer reported that Phase II AMD/AML right-of-ways are secured for 28 of 34 parcels and an environmental assessment was submitted on 10/23/25; the Chub Run sewer extension and Phase IV sewer connection await scheduling and regulatory approvals.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
In a written engineer report, staff said the Phase II AMD/AML project has secured 28 of 34 right-of-way agreements and that the environmental assessment was submitted to the Office of Surface Mining on Oct. 23, 2025, with the project aiming to go out for bid by year-end. The Chub Run Sewer Extension contractor was scheduled to start around Nov. 1 but staff indicated the start will likely be delayed until later in the year; Phase IV sewer work is awaiting PSC and DEP approvals for a connection at Sandy’s Hardware station.
Councilors received the written updates and did not take formal action during the meeting. The engineer's report documents progress on property acquisition and regulatory filings and notes the likelihood of construction scheduling changes due to approvals and contractor availability.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.