Board gets timeline on drainage work; contingency to cover unexpected repairs

Jun 23, 2026

District Engineer reported all four drainage sites are under construction with sod and pipe schedules into late June/early July; contractors hit an A/C coolant line during clearing and the Board was told repair costs will come from contingency funds.

The full story

District Engineer Charlie Krebs told the River Ridge board on June 23 that all four drainage improvement sites are under construction and that crews have installed silt fences, staged fill and placed pipe. He said Palmetto Dunes is expected to be completed by the end of the week, sod installation in Turnberry and Palmetto Dunes is anticipated the week of July 2, 2026, and pipe installation in Oak Run is scheduled for the week of June 29, 2026.