Engineering Plus: Regulator-station plans near bidding stage; water-line work progressing

Jul 15, 2025

Engineering Plus reported that plans for a new regulator station location are being finalized and are in the last stage before bidding; environmental coordination with TVA is underway and water-line construction continues on schedule and within funding timelines despite weather delays.

The full story

Richmond Alexander of Engineering Plus (participating telephonically) told the Kemper County Utility District on July 15 that plans for a new regulator-station location are being finalized and the project is approaching the bidding stage. Alexander said Terrell Temple has been in discussions with the Tennessee Valley Authority about the environmental work needed at the regulator site.