Board hears progress on bond-funded projects, marquees and roofing
May 14, 2026
Facilities staff updated trustees on bond projects: foundations and drainage for ballfields, a 90-calendar-day target for new digital marquees, playground lead times of 8–10 weeks, roofing side-panel change orders and bleacher/flooring orders for upcoming summers.
The full story
District facilities staff told the board that bond-funded projects are moving forward: foundations and drainage are in place at the baseball and top fields; roofing crews have begun panel work at the high school; and the district expects to receive playground equipment in roughly 8–10 weeks after manufacture.