Engineer reports: AMD project pay application, ROWs in hand for Phase 2, Chub Run on hold with possible Oct. 1 start

Town of Nutter Fort Town Council · August 26, 2025

Summary

The town engineer reported Phase 1 AMD pay-application comments are nearing completion, Phase 2 shows '20/34 ROWs in hand' and awaits an OSM environmental clearance, Chub Run remains on hold with a potential Oct. 1 start, and Phase IV waits DEP clearance for Sandy's hardware forcemain work.

Town engineering staff updated council on multiple public-works projects, outlining near-term milestones and environmental clearances needed for construction.

For the AMD work, Phase 1 pay-application comments are being finalized and the engineer expects it to be ready for drawdown at the September meeting. For Phase 2, the minutes state "20/34 ROW's in hand" and note the project is awaiting an environmental assessment clearance from the Office of Surface Mining (OSM); the engineer expects to be out to bid by the end of the year if clearances are secured.

Chub Run remains on hold but the engineer listed a potential Oct. 1 start date. Phase IV is awaiting environmental clearance from the West Virginia Department of Environmental Protection related to the Sandy's hardware forcemain work. The Nutter Run permitting Task Order #7 was recorded as complete elsewhere in the minutes.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source