CALIF modernization testing begins; mock session scheduled for September

Aug 10, 2026

Project presenter Altaf told the LCC that a user-acceptance testing build from Propellon has been received and testing has started; testing will run about four weeks with a mock end-to-end session scheduled around mid-to-late September.

The full story

Altaf, the project presenter for the CALIF modernization project, told the council the user-acceptance test build from Propellon has been received and testing has begun. "We have received that build, and today, we have started that thorough testing, which will go on at least for 4 weeks or so," Altaf said. He added that, if only minor issues are found, Propellon will fix them and that a mock session to confirm end-to-end functionality is planned for roughly mid-to-late September.