District reviews stadium lighting, paving and retaining‑wall estimates under 2024 bond
Aug 11, 2025
Gallagher Construction presented estimates for lighting upgrades (~$129,000), three parking‑lot paving projects (Lot 1 ≈ $750,000 for ~70,000 sq. ft.; Lot 3 ≈ $550,000; Lot 4 ≈ $650,000) and a retaining wall ($75,000–$100,000). Trustees asked for neighbor outreach and additional cost estimates for ventilation improvements at the CTE building.
The full story
Claire Saenz of Gallagher Construction presented preliminary designs and cost estimates for projects funded under the 2024 School Project Bond, including stadium and parking lot lighting, extensive paving and a retaining wall near visitor parking. The lighting scope would use existing stadium poles for Lots 1 and 2 with outward‑facing fixtures and require one new pole each for Lots 3 and 4; Saenz estimated the lighting package at about $129,000. The paving estimates included Lot 1 (about 70,000 square feet) at roughly $750,000, Lot 3 at about $550,000 and Lot 4 at about $650,000. Saenz also estimated the retaining wall at $75,000–$100,000.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →