Treasurer reports progress on Governor Stable Road bridge projects; engineering responsiveness flagged

Conoy Township Board of Supervisors · August 14, 2025

Summary

Treasurer Jennifer Rabuck reported the GP-11 permit has been approved for the Governor Stable Road Bridge Infrastructure Phase 1 ($320,000) and Hanover Engineering is drafting construction plans but has been unresponsive to email. DM/A is finalizing preliminary design for Bridge 2.

Treasurer Jennifer Rabuck updated the board on several grant-funded road and bridge projects tied to the 2023 Multimodal Transportation Fund.

Rabuck said the Governor Stable Road Bridge Infrastructure and Realignment Phase 1 project has $320,000 in funding and a General Permit (GP-11) has been approved. She told the board that Hanover Engineering has been preparing construction plans but has been unresponsive to email inquiries about project status. Rabuck also said DM/A is wrapping up preliminary design work for Governor Stable Road Bridges 2 and 3.

Separately, the board heard that stone has been laid at the 738 Stackstown Road parking lot and paving was expected by month’s end. The minutes record concern about contractor responsiveness on the Phase 1 bridge plans but do not record a motion or formal direction to change consultants.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source